Update...
We got planning approval from council.
We had to upgrade the house insulation and windows to get energy effiency certification
- Change all windows and glass doors to E-Glass, change 1 glass door to double glazing, add sisalation to the roof, upgrade ceiling insulation from 4.0 to 5.0, add internal insulation to all internal walls
= $5000 extra
We got energy effiency certification
We got building certification
We got development/building approval from council
The builders should be starting to build in approx 3 weeks-ish
Also I have put the shed planning/building application into council
- I was waiting on the energy upgrade price before commiting to the shed, I can go ahead with the shed I want as it's still in budget.
THE SHED...
7.6M x 12M colourbond, 2 sliding doors in the gable end, 1 PA door, roof insulation, cement floor, 3 phase power connected and lights/power points installed.